Judgment of the Court (Eighth Chamber) of 8 May 2025. – European Commission v Republic of Slovenia. – Failure of a Member State to fulfil obligations – Environment – Directive 1999/31/EC – Landfilling of waste – Directive 2008/98/EC – Waste management – Judgment of the Court of Justice establishing a failure to fulfil obligations – Partial non-compliance – Article 260(2) TFEU – Pecuniary penalties – Lump sum. – Case C-318/23.
ECLI: ECLI:EU:C:2025:342Decision of: 08.05.2025
Amtliche Leitsätze
Judgment of the Court (Eighth Chamber) of 8 May 2025 –
Commission v Slovenia (Bukovžlak landfill)
(Case C‑318/23)
(Failure of a Member State to fulfil obligations – Environment – Directive 1999/31/EC – Landfilling of waste – Directive 2008/98/EC – Waste management – Judgment of the Court of Justice establishing a failure to fulfil obligations – Partial non-compliance – Article 260(2) TFEU – Pecuniary penalties – Lump sum)
1. Actions for failure to fulfil obligations – Judgment of the Court establishing the failure of a Member State to fulfil its obligations – Period for implementation – Compliance having to be initiated at once and completed as soon as possible – Delay in compliance with a judgment concerning the landfilling of waste – Justification – None (Art. 260(1) TFEU; European Parliament and Council Directive 2008/98; Council Directive 1999/31) (see paragraphs 35, 38-43, 79)
2. Actions for failure to fulfil obligations – Judgment of the Court establishing the failure of a Member State to fulfil its obligations – Period for implementation – Reference date for assessing whether there has been a failure to fulfil obligations – Date of expiry of the period prescribed in the letter of formal notice (Art. 260(2) TFEU) (see paragraphs 36, 37)
3. Actions for failure to fulfil obligations – Judgment of the Court establishing the failure of a Member State to fulfil its obligations – Breach of the obligation to comply with the judgment – Pecuniary penalties – Purpose – Prevention of the repetition of similar infringements (Art. 260(2) TFEU) (see paragraphs 62, 63)
4. Actions for failure to fulfil obligations – Judgment of the Court establishing the failure of a Member State to fulfil its obligations – Breach of the obligation to comply with the judgment – Pecuniary penalties – Imposition of a lump sum payment – Discretion of the Court – Criteria for assessment (Art. 260(2) TFEU) (see paragraphs 64-67, 83)
5. Actions for failure to fulfil obligations – Judgment of the Court establishing the failure of a Member State to fulfil its obligations – Breach of the obligation to comply with the judgment – Pecuniary penalties – Lump sum – Calculation of the amount – Criteria – Gravity of the infringement – Prolonged failure to comply with the judgment of the Court – Fundamental nature of the provisions which are the subject of the failure to fulfil obligations that was established – Failure to comply with a judgment concerning the landfilling of waste – Mitigating circumstances (Art. 260(2) TFEU) (see paragraphs 68-76, 83)
6. Actions for failure to fulfil obligations – Judgment of the Court establishing the failure of a Member State to fulfil its obligations – Breach of the obligation to comply with the judgment – Pecuniary penalties– Lump sum – Calculation of the amount – Criteria – Duration of the infringement – Assessment at the date of examination of the facts by the Court (Art. 260(2) TFEU) (see paragraphs 77, 78, 80, 83)
7. Actions for failure to fulfil obligations – Judgment of the Court establishing the failure of a Member State to fulfil its obligations – Breach of the obligation to comply with the judgment – Pecuniary penalties – Lump sum – Calculation of the amount – Criteria – Payment capacity – Date of assessment (Art. 260(2) TFEU) (see paragraphs 81-83)
Operative part
The Court:
1. Declares that, by failing to take the measures necessary to comply with the judgment of 16 July 2015, Commission v Slovenia (C‑140/14, EU:C:2015:501), as regards plot no 115/1 in the municipal land register of Teharje (Bukovžlak), the Republic of Slovenia has failed to fulfil its obligations under Article 260(1) TFEU;
2. Orders the Republic of Slovenia to pay to the European Commission a lump sum in the amount of EUR 1200000;
3. Orders the Republic of Slovenia to pay, in addition to its own costs, those incurred by the European Commission.