EU Case-Law · General Court of the European Union

Judgment of the General Court (Ninth Chamber) of 27 September 2023. – Fundación Imdea Materiales v European Commission. – Arbitration clause – Seventh Framework Programme for research, technological development and demonstration activities (2007-2013) – Grant agreement – ‘Compound Semiconductors for 3D integration’ project – Repayment of sums paid – Payment of damages – OLAF investigation report – Debit notes – Eligible costs – Reality of the costs – Reliability of timesheets – Alternative evidence – Proportionality. – Case T-765/21.

ECLI: ECLI:EU:T:2023:588Decision of: 27.09.2023

Amtliche Leitsätze

Judgment of the General Court (Ninth Chamber) of 27 September 2023 – Imdea Materiales v Commission (Case T‑765/21) ( 1 ) (Arbitration clause – Seventh Framework Programme for research, technological development and demonstration activities (2007-2013) – Grant agreement – ‘Compound Semiconductors for 3D integration’ project – Repayment of sums paid – Payment of damages – OLAF investigation report – Debit notes – Eligible costs – Reality of the costs – Reliability of timesheets – Alternative evidence – Proportionality) 1. Judicial proceedings – Application initiating proceedings – Formal requirements – Identification of the subject matter of the dispute – Brief statement of the pleas in law on which the application is based – Failure to specify in the application the arguments relating to the right to a fair procedure – Inadmissibility (Statute of the Court of Justice, Arts 21, first para., and 53, first para.; Rules of Procedure of the General Court, Art. 76(d)) (see paragraphs 27, 35) 2. EU budget – EU financial assistance – Obligation on the beneficiary to comply with the conditions for grant of the assistance – Seventh Framework Programme for research, technological development and demonstration activities (2007-2013) – Grant agreement – Audit procedure and control procedure – Investigation carried out by the European Anti-Fraud Office (OLAF) – Differentiation between an OLAF investigation and a financial audit – No obligation to send OLAF’s investigation file to the applicant (Art. 317 TFEU; European Parliament and Council Regulation No 883/2013, Art. 3) (see paragraphs 46-48, 51, 54, 55, 61, 65, 69) 3. EU budget – EU financial assistance – Obligation on the beneficiary to comply with the conditions for grant of the assistance – Funding only for expenses actually incurred – Demonstration that the costs have actually been incurred – Allocation of the burden of proof (Art. 317 TFEU) (see paragraphs 81-85, 99, 101-103) 4. EU budget – EU financial assistance – Obligation on the beneficiary to comply with the conditions for grant of the assistance – Funding only for expenses actually incurred – Demonstration that the costs have actually been incurred – Staff costs – Production of time records – Failure to comply with the general conditions (Art. 317 TFEU) (see paragraphs 106, 110) 5. EU budget – EU financial assistance – Obligation on the beneficiary to comply with the conditions for grant of the assistance – Funding only for expenses actually incurred – Demonstration that the costs have actually been incurred – Evidence put forward by the beneficiary – Assessment (Art. 317 TFEU) (see paragraphs 116-120, 130, 167) 6. EU budget – EU financial assistance – Obligation on the beneficiary to comply with the conditions for grant of the assistance – Justification of costs incurred – Proceedings by the Commission for recovery of advances paid – Recovery of funding for costs found to be ineligible – Commission’s refusal to recover in part subsidies paid – No breach of the principle of proportionality (Art. 317 TFEU) (see paragraphs 174, 179-182) 7. EU budget – EU financial assistance – Obligation on the beneficiary to comply with the conditions for grant of the assistance – Justification of costs incurred – Proceedings brought by the Commission for the payment of damages – No breach of the principle of proportionality (Art. 317 TFEU) (see paragraphs 188, 191) Operative part The Court: 1. Dismisses the action; 2. Orders Fundación Imdea Materiales to pay the costs. ( 1 ) OJ C 73, 14.2.2022.

© Europäische Union, https://eur-lex.europa.eu · CELEX 62021TJ0765

Official language versions

This decision is available in the following official languages of the Union — all equally authentic.

EnglishEspañolFrançaisItaliano