Judgment of the General Court (Sixth Chamber) of 20 May 2019. – Fundación Tecnalia Research & Innovation v Research Executive Agency (REA). – Arbitration clause — Grant agreement concluded in the framework of the Seventh Framework Programme for research, technological development and demonstration activities (2007-2013) — Development of a system to monitor process and quality in the sector of industrial food production — Food-Watch Project — Overlap of the project with another project funded under the same programme — Information requirements on beneficiaries — Decision to demand repayment of the financial contribution paid under the grant agreement. – Case T-104/18.
ECLI: ECLI:EU:T:2019:345Decision of: 20.05.2019
Amtliche Leitsätze
Judgment of the General Court (Sixth Chamber) of 20 May 2019 –
Fundación Tecnalia Research & Innovation v REA
(Case T‑104/18)
(Arbitration clause — Grant agreement concluded in the framework of the Seventh Framework Programme for research, technological development and demonstration activities (2007-2013) — Development of a system to monitor process and quality in the sector of industrial food production — Food-Watch Project — Overlap of the project with another project funded under the same programme — Information requirements on beneficiaries — Decision to demand repayment of the financial contribution paid under the grant agreement)
1. Judicial proceedings — Legal basis of an action — Choice for the applicant and not the EU judicature (Arts 263 and 272 TFEU) (see para. 39)
2. EU law — Principles — Principle of sound administration (Art. 272 TFEU) (see paras 67, 71)
3. EU law — Principles — Rights of the defence — Whether applicable to administrative procedures initiated by the Commission — Scope — Application to a procedure for recovering debts of contractual origin in respect of a recipient of European funds — Not included (Art. 272 TFEU; Charter of Fundamental Rights of the European Union, Arts 47 and 48) (see paras 72, 73)
4. Action for annulment — Pleas in law — Infringement of essential procedural requirements — Obligation to state reasons applying only to unilateral means of action — No obligation to state reasons in the framework of a grant agreement (Arts 272 and 296 TFEU) (see para. 78)
5. Acts of the institutions — Statement of reasons — Obligation — Scope — Specific programme for research, technological development and demonstration activities — Commission’s request for reimbursement of the financial contribution paid pursuant to a research grant agreement concluded in that context — No obligation to state reasons (Arts 288 and 296 TFEU; Charter of Fundamental Rights of the European Union, Art. 41(2)(c)) (see para. 79)
6. Judicial proceedings — General Court seised under an arbitration clause — Pleas in law — Lack of or inadequate statement of reasons — Invalid plea in law — Rejection (Arts 272 and 296 TFEU) (see para. 80)
7. Procedure — General Court seised under an arbitration clause — Grant agreement concluded in the framework of a specific programme for research, technological development and demonstration activities — Overlap of the subsidized project with another project funded under the same programme — Unilateral termination of the agreement due to a breach of the contractual terms concerning the beneficiaries’ information requirement — Request for reimbursement of the financial contribution paid pursuant to the grant agreement — Joint and several liability of contractors — Scope (Art. 272 TFEU) (see paras 109-112, 114, 118, 131-136)
8. Procedure — General Court seised under an arbitration clause — Grant agreement concluded in the framework of a specific programme for research, technological development and demonstration activities — Overlap of the subsidized project with another project funded under the same programme — Unilateral termination of the agreement due to a breach of the contractual terms concerning the beneficiaries’ information requirement — Possibility for the Commission to recover the European Union’s financial contributions in full — Conditions (Art. 5(4) TEU; Arts 272 and 274 TFEU) (see paras 141, 143-147)
Re:
Application based on Article 272 TFEU seeking, in essence, a declaration that the applicant is not required to repay the grant awarded for the project FP7-SME 2013 605879 (Food-Watch).
Operative part
The Court:
1. Dismisses the action;
2. Orders Fundación Tecnalia Research & Innovation to pay the costs, including those of the interim proceedings.